The LON Family EXTREME Home Makeover - One
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
![]() |
![]() |
|---|
The demands and strains on this family are unbelievable! In order to navigate Christian up to his bedroom or out to the car for a trip to his treatments, they are literally having to drag him up and down flights of stairs on his behind. Greg and Bernie have visited this family a couple of times and have created a plan to remodel a bedroom, move a bathroom, and create a new laundry room on the first floor of their home. It costs more than we have, will require a level of planning and ommitment that we’ve never done before, while we are in a really bad economy. Even if it somehow gets done it WON’T change the orld! But it will DEFINITELY change the Lon Families future. They will know that they aren’t alone in dealing with an mpossible situation every day of the rest of their lives. They will know that Jesus knows about their circumstance and that He cares. By serving we will be served. So, because and only because, we are thoroughly convinced we are joining a ‘God-activity’ we are going to take a step of faith and we are going for it!
So here is the ‘ask’ – are you willing to join Bernie Thompson, Greg Lueck, and me in doing an EXTREME Home makeover for this family? It is a crazy ‘bigger than us’ God-adventure. At the end of your life when you are reflecting on the things that made it all worth it – I can guarantee you that whatever investment you make in this project will be part of that legacy. Jesus tells us that pure religion is helping the widow and orphans. In other words helping those who can’t help themselves and who won’t survive if someone doesn’t care. All I can say is, “Give me some of that!!” Who will join me?
Here are the specific things needed a) A demolition team for Saturday b) Skilled crews willing to sign up starting Monday and going through Friday – we have identified the various skill sets needed c) support teams during the week – meals and site clean up d) Building materials – we have a list in the lobby e) Money donations – NOT tithe and NOT local church ministries giving! f) prayer support – we are fasting this Wednesday as we plan to take this faith step!
In HIM,
Paul
Project: Lon Family EXTREME Home Makeover
Where: 1 Doxdam Ct – Germantown, MD 20876-4172
When: Starting Jan 17th at 7am and ending Jan 24th at 4:00pm
Contact No: Bernie Thompson 301 639-5943 (project manager)
Greg Lueck 240 446-6911 (project manager)
Paul Foss 240 485-2650 (communication & donations)
Needed Materials: (Please contact either Bernie Thompson or Greg Lueck
2x4’s Vanity
2x6’s Tile for tub area
Plywood Lights
Insulation Outside door
Drywall Inside doors
Paint Cement
Electrical Linoleum
Counter Top Carpet
Microwave Commercial washers & dryers (stackable)
Refrigerator Handicap Tub
Cabinets Toilet
Work Crews: (Please contact Paul Foss)
Friday Jan 16th |
4-7pm |
Setup for next day |
2-4 men |
_________________ |
Saturday Jan 17th |
7am-4pm |
Demolition & Framing |
8-10 people (Skilled & Unskilled) |
__________________ |
|
|
Plumbing rough-in |
2-4 men (Skilled & Muscle guys |
__________________ |
Monday Jan 19th |
7am-4pm |
Plumbing rough-in |
2-4 men (Skilled & Muscle guys |
__________________ |
|
7am-3pm |
Framing, electrical |
2-4 men |
_________________ |
Tuesday Jan 20th |
7am-3pm |
Framing, electrical |
2-4 men |
_________________ |
|
4pm-8pm |
Framing, electrical |
4-6 men |
_________________ |
Wednesday Jan 21st |
7am-3pm |
Drywall, doors |
2-4 men |
_________________ |
|
4pm-8pm |
Drywall, doors |
4-6 men |
_________________ |
Thursday Jan 22nd |
7am-3pm |
Drywall, doors |
2-4 men |
__________________ |
|
4pm-8pm |
Drywall, doors |
4-6 men |
_________________ |
Friday Jan 23rd |
7am-3pm |
Finish - paint |
2-4 men |
_________________ |
|
4pm-8pm |
Finish - paint |
4-6 men |
_________________ |
Saturday Jan 24th |
7am-5pm |
Flooring, Fixtures |
6-8 men |
_________________ |
|
|
Electrical |
2-4 men |
_________________ |
|
|
|
|
|